Subject:
Title
Consider a budget reallocation for the Public Works Department in the amount of $166,000 for the East Market Street Stormwater Improvement project.
body
Presented By: Thomas Hartman, PE, Assistant Director of Public Works.
Recommendation and Review
The Department of Public Works (DPW) requests a budget reallocation of $166,000 from the Sampson Park Stormwater Capital Project to the East Market Street Stormwater Improvement Capital Project. This reallocation will allow the DPW to expand this existing project to include an additional bioretention basin near the intersection of East Market Street and Country Club Road. This additional bioretention basin will increase the annual phosphorus removal by roughly 4 lbs annual, bringing the total to 22.5 lbs of phosphorus removed annually.