Subject:
Title
Presentation on the N. Mason Street Complete Streets Demonstration Project
Body
Presented By: Amy Snider, City Manager’s Office and Tom Hartman, Department of Public Works
Recommendation and Review
The N. Mason Street Complete Streets Demonstration Project is a product of the Community Connectors Program and the Complete Streets Leadership Academy. City staff and residents of the Northeast Neighborhood collaboratively designed a road reconfiguration of N. Mason Street to be implemented as a demonstration project in July 2025. This presentation will share about the Complete Streets Leadership Academy and provide an overview of the upcoming temporary changes to N. Mason Street as part of the demonstration project. This item is informational only and requires no action.