Consider adopting a resolution authorizing Harrisonburg Electric Commission to enter into a Battery Energy Storage System Output Purchase Agreement and Interconnection Agreement for Battery Energy Storage Facility for a term in excess of 10 years.
Body
Presented By: Chris Brown, City Attorney
Recommendation and Review
The Harrisonburg Electric Commission (HEC) desires to participate in a battery energy storage system project (the “BESS Project”), where a BESS system would be installed and interconnected with HEC’s electric facilities. The BESS Project will reduce the peak load of Virginia Municipal Electric Association No. 1 (“VMEA”), which will enable significant cost savings. Those savings will be apportioned to VMEA members, including HEC.
Section 8-1-11 of the City Code of the City of Harrisonburg, Virginia requires City Council approve any HEC contracts or agreements that exceed 10 years in duration.